nutricia 1

Adaptations Nutricia Factory 1

See pictures

Project information

Project description:

Nutricia has made a step forward in fire safety and has fitted various factory sections, amongst which Factory 1, with a sprinkler system. An adaptation of the roof in order to improve the slope was part of the sprinkler project. Additionally, other (fire) safety installations were installed, such as fire alarms and evacuation installations, fire hose winches and an emergency lighting installation.

 

Delmeco’s work for Nutricia encompassed consultancy and construction management in order to come to an integral agreement between the parties involved, such as governmental bodies, inspection institutes, insurer and owner Nutricia NV.

 

The assignment consisted of various aspects that have common ground with various disciplines such as construction, mechanical engineering and electrical engineering.

  • Drawing up an inventory and technical specifications for project realisation, including consultancy;
  • Drawing up an investment estimate;
  • Inviting quotations, judging quotations and consultancy regarding selection;
  • Attuning Nutricia, fire brigade, insurer, production and other parties involved, including project planning;
  • Construction management and project management operational phase;
  • Checking drawings and specifications;
  • Ensuring adequate completion for Nutricia.

In this project it was Delmeco’s responsibility to manage all disciplines, including managing contractors in order to get to a successful operational system that meets the client´s wishes and demands.

Client: Nutricia NV

Nutricia NV is one of the world’s most prominent food product businesses as a part of the Groupe Danone. Nutricia is market leader in the Dutch clinical nutrition market. They specialise in enteral nutrition for children with brands such as Nutrini, NutriniDrink and NutriniMax.

Delmeco Raadgevend Ingenieurs bureau

Marquesweg 4
4462 HD Goes, The Netherlands
info@delmeco.nl

+31 (0)113-270484